How Long Does a Kitchen Remodel Take? Phases and Timeline

By John Williams, Lead Technician10 min read

Long open kitchen in Montgomery, Ohio with cherry Shaker cabinets, white counters, white herringbone tile, floating wood shelves and an island on light hardwood floors

Key Takeaways

  • With Bulldog, a full kitchen remodel usually runs 4 to 8 weeks from first design meeting to final walkthrough, and you get your dates in writing before we start.
  • Houzz's 9.6 months of planning and 5.1 months of building are homeowner-reported averages for 2023 projects. Our read: the planning figure likely covers the homeowner's whole decision period, including time before a contractor is hired.
  • Design and selections set the pace. A kitchen with every product chosen before the contract moves faster than one with open allowances.
  • Moving walls, plumbing or gas adds permits, trades and inspections. In Ohio, rough work is inspected before the walls close.
  • Countertops are measured off the installed cabinets, so cabinets always come before stone.

With Bulldog Remodel Group, a full kitchen remodel usually takes 4 to 8 weeks from the first design meeting to the final walkthrough, depending on your selections and material lead times. National surveys report far longer numbers. In Houzz's 2024 Houzz & Home Study, homeowners who renovated a kitchen in 2023 reported an average of 9.6 months of planning and 5.1 months of building.

The two figures cover different windows. Houzz's numbers are homeowner-reported, and in our reading its planning months likely include the homeowner's whole decision period, often before any contractor is involved. The rest of this guide walks through each phase in order, what sets its length, and what you can do to keep your own kitchen remodel timeline on track. The kitchen at the top is our Montgomery cherry kitchen, where removing walls opened the room to the living spaces next to it.

The kitchen remodel timeline at a glance

A kitchen remodel moves through five phases. The first three happen before anyone picks up a hammer, and they decide how smoothly the last two go.

Phase What happens What sets the length
1. First call and walkthrough Phone call, in-home visit, budget range A 15 to 20 minute call and a 30 to 60 minute visit, scheduled around your availability
2. Design and selections Layout drafts, cabinets, counters, tile, fixtures, fixed-price agreement How quickly decisions get made
3. Ordering, permits and staging Materials ordered, permits applied for, everything delivered before demo Cabinet and material lead times and permit review
4. Construction Demolition through final inspection Dates are set in your written schedule before demo. Four things set them: scope, cabinet and material lead times, required inspections and any older-home repairs
5. Walkthrough Final check, punch list, warranty paperwork Punch list items

With Bulldog, our usual window runs from the first design meeting to the final walkthrough, which covers phases 2 through 5. Every kitchen is planned around a different household and scope. Your fixed-price construction agreement covers scope, schedule and payment terms, and you get your dates in writing before we start.

Phase 1: the first call and the in-home walkthrough

The first call takes 15 to 20 minutes. We ask where your home is, what you want to remodel, why now, when you would like it done and what you are comfortable investing.

The in-home walkthrough takes 30 to 60 minutes. We listen to your goals, look at the room and talk through a realistic budget range. From there, we schedule a follow-up to present selections, a basic layout and a 3D rendering, or we move straight into a design agreement. Sometimes we agree we are not the right fit, and that is fine too.

You can shorten this phase by doing homework first: gather photos of kitchens you like, decide whether the footprint stays, and set a working budget. Our kitchen remodel planning guide has a checklist for that.

Phase 2: design and selections

Design is the phase that most often stretches a kitchen schedule, because every later step waits on it. Our designers produce a few rough drafts so you can react, refine and react again, and we settle the layout before talking about specific finishes.

Then come the selections: cabinets, tile, countertops, plumbing fixtures, paint colors and hardware. Everything is chosen before construction starts. While you choose finishes, our team finalizes measurements, drawings and code details so the crew has a complete plan on day one. The phase ends with a fixed-price construction agreement that covers scope, schedule and payment terms, and any design fees credit toward your first construction payment.

Kitchen with greige wood cabinetry, a matching wood range hood, stacked wall ovens, a stainless refrigerator and a slate blue island with a speckled stone top
Custom greige cabinetry, a matching wood hood and a slate blue island in our Clifton, OH kitchen remodel.

To keep this phase short:

  • Choose appliances first. The range, refrigerator, dishwasher and hood set the cabinet sizes and the electrical, gas and venting work. Changing an appliance after the cabinet drawings are done sends the drawings back. Countertop makers want them settled early too: Cambria's installation guidance says sinks, faucet fixtures and appliances "should be available at the site" for final measurements (Cambria).
  • Pick real products. An allowance that says "tile, to be selected" turns into a decision in the middle of construction, when it costs the most time.

Phase 3: ordering, permits and staging

Lead time is the wait between placing an order and the material arriving at your house. Cabinets usually carry the longest one. Stock cabinets come in fixed sizes, semi-custom adds more sizes and finishes, and custom cabinets are built to your exact dimensions, so built-to-order boxes take longer to arrive than stock. Once the agreement is signed, we order and stage all materials, verify final measurements and schedule our in-house crew before day one.

Any kitchen work that changes electrical, plumbing, gas or structure needs a permit, and permit applications and inspection visits are handled on our side. Each building department sets its own review time. As one example from a Northern Kentucky office, Planning and Development Services of Kenton County lists 12 business days to process residential permits and 5 business days for electrical permits. The office notes that "permit approval times may vary depending on the workload" (PDS of Kenton County). Its list of work that needs no permit includes "Finish work such as painting, tiling, and cabinets." Ohio departments, including Cincinnati's, set their own review times.

We pull every required permit with the right Ohio, Kentucky or Indiana building department and coordinate every inspection. For the rules in each area, read which kitchen remodels need a permit in Cincinnati and Northern Kentucky.

Before work starts, we hold a pre-construction meeting to walk through parking, dumpster placement, pets, daily start times and dust control.

Phase 4: construction, step by step

A typical kitchen build follows this order, because each step depends on the one before it:

  1. Floor protection, dust control and demolition. Old cabinets, counters and flooring come out and get hauled away.
  2. Repairs. Rot, sags and old notching get fixed before new cabinets go in, so the cabinets sit on a sound, level floor.
  3. Rough-in. New plumbing lines, wiring, circuits and any gas line go in while the walls are open.
  4. Rough inspections. The inspector checks the new work before it is covered.
  5. Drywall. Walls close up and get finished.
  6. Flooring and cabinets. The floor and the cabinet boxes go in.
  7. Countertops. The fabricator templates the installed cabinets, then cuts and sets the stone.
  8. Backsplash, fixtures and appliances. Tile goes up, the sink and faucet are connected, and appliances are installed.
  9. Paint, hardware and trim. The finishing details.
  10. Final inspection. The building department signs off on the permitted work.

Rough-in is the plumbing, wiring, gas and duct work that runs inside the walls and floor before they are closed. The Residential Code of Ohio sets when it gets checked. The framing inspection happens once framing is in place "and the rough electrical, plumbing, heating wires, pipes and ducts are approved" (Section 108.2.5). Where a drywall inspection is required, it comes "before gypsum board joints and fasteners are taped and finished" (Section 108.2.6).

The same chapter says the building official gives the owner, or the owner's representative, "a list of all required inspections for each project" when plan approval is issued (Section 108.2) (Residential Code of Ohio, Chapter 1, via UpCodes). Your local department can confirm which code edition and inspections apply at your address.

Templating is the step where the countertop fabricator measures the finished cabinet run to make an exact pattern for the stone. That is why counters always follow cabinets. Cambria's installation guidance says "All cabinets must be permanently installed and in the same plane" before final measurements (Cambria).

On our kitchens, your project manager oversees demolition, cabinetry, countertops, tile, plumbing, electrical and finishing, with daily updates throughout. Our in-house W-2 craftsmen handle the work from demolition through final hardware, and your project manager is on site daily and one text away.

Kitchen with warm wood base cabinets, white upper cabinets, a black chimney range hood, a furniture-style wood island with a white top and glass globe pendants
Warm wood base cabinets under white uppers in our Oakley, OH kitchen remodel.

During this phase you will not have a working kitchen. Most families set up a temporary one in another room with the fridge, a microwave, a coffee maker and a folding table, and we help you plan it before demolition. Living without a kitchen during the remodel has a full checklist.

Phase 5: the final walkthrough

The last day is a walkthrough. We walk through the finished kitchen with you, finish any punch list items, professionally clean your home and hand over your warranty packet and care guidelines. If a defect in our work ever shows up, we make it right.

Why national survey numbers look so much longer

Houzz's numbers come from a survey of 32,615 Houzz users, including 17,713 renovating U.S. homeowners. Kitchen renovations had the longest timeline of any room in 2023: 9.6 months of planning and 5.1 months of building on average. Living rooms came next at 8.1 months of planning and 4.1 months of building (Houzz, 2024).

Average months of planning and building on 2023 projects, Houzz 2024 study: kitchen 9.6 months planning and 5.1 months building; living room 8.1 months planning and 4.1 months building
Source: Houzz, 2024 U.S. Houzz & Home Study: Renovation Trends, March 27, 2024.

The kitchen figures were similar two years earlier. For 2021 projects, Houzz reported that "planning a kitchen remodel took an average of 8.6 months, while construction took 4.9 months" (Houzz Pro).

Our read of the report: the survey and a contractor's schedule measure different windows. Houzz's figures are what homeowners reported, and the planning months likely cover their whole decision period, including the time before any contractor is hired. Houzz itself notes that homeowners "dedicate about twice as much time on average to the planning phase." Our schedule window starts at the first design meeting, after much of that early thinking is done. The surveys also cover every kind of project and contractor, so they describe a national average rather than the schedule for any single kitchen.

What makes a kitchen remodel take longer

Each of these adds time to a kitchen schedule:

  • A layout change. Moving the sink, range or a wall adds plumbing, gas, electrical and sometimes structural work, plus the inspections that go with it. Keeping the sink, range and dishwasher where they are avoids those extra trades.
  • Removing a load-bearing wall. A beam has to be sized and installed, and the opening inspected. See taking out a load-bearing wall for an open kitchen.
  • An older house. Repairs can add work before the new kitchen goes in. In an older home, we check the panel, wiring, plumbing, subfloor and walls before anything is priced, and rot, sags and old notching get fixed before new cabinets go in. Any of that work is built into the written schedule you get before demo.
  • Late decisions. Every selection left open after the contract is a chance for a delay.
  • Custom cabinets. Built-to-order cabinets take longer to arrive than stock or semi-custom. Ordering them early keeps that wait out of the construction phase.

How to keep your kitchen remodel on schedule

You control more of the timeline than you might think:

  1. Make your selections during design, and stick with them.
  2. Choose appliances before the cabinet drawings are final.
  3. Clear the kitchen and set up a temporary one before demolition day.
  4. Answer questions from your project manager the same day when you can.
  5. Plan travel and big events outside the construction phase.

Frequently asked questions

How long does a kitchen remodel take from start to finish?

With Bulldog, the full process from the first design meeting to the final walkthrough usually takes 4 to 8 weeks, depending on your selections and material lead times. You get your dates in writing before we start.

How long will I be without a kitchen?

You are without a working kitchen from demolition until the sink, counters and appliances are back in. Your construction dates are set in your written schedule before demo. Four things set them: the scope (keeping the sink, range and dishwasher in place, or moving plumbing, gas or walls), cabinet and material lead times, required inspections, and any repairs an older house needs. We stage every material before demo day to keep that stretch as short as possible.

Why do national surveys show kitchens taking much longer?

Survey figures are homeowner-reported, and in our reading the planning months likely include time before a contractor is involved. Houzz found that homeowners spent about twice as long planning as building: kitchen renovations averaged 9.6 months of planning and 5.1 months of building in 2023.

Does a permit slow down a kitchen remodel?

It adds review time before work starts and inspection visits during it. As one Northern Kentucky example, PDS of Kenton County lists 12 business days for residential permits and 5 for electrical permits, and approval times vary with its workload. Ohio departments, including Cincinnati's, set their own review times. Applying as soon as the plans are final keeps review from holding up the start date.

Get a schedule for your kitchen

Book an in-home consultation and we will walk the room, talk through your layout and budget, and give you an itemized, fixed price with your dates in writing. You can also see our kitchen remodels, read how our process works, or call us at (513) 657-3750.

Sources

What homeowners in Greater Cincinnati say about Bulldog Remodel Group

Oakley, Cincinnati, OH · Whole-Home Remodel

Kristen Vance

My name is Kristen Vance, and my husband, our son Louis, and I have lived in our home for 15 years. We fell in love with this 1950s home as soon as we saw it, but it definitely needed updating. Remodeling for the first time was a big decision, and Bulldog stood out from every other contractor we considered. Looking back, choosing them was one of the best decisions we made. What means the most to me is the trust they earned. They didn’t just remodel our kitchen or bathroom. They transformed our entire home. Every detail was completed with quality, and I have complete peace of mind knowing everything was built the right way. We love entertaining here because we’re so proud of the finished result. Quality is worth investing in, and Bulldog proves that you truly get what you pay for. It was an amazing experience, and I’d happily do it all over again.
“I highly recommend Bulldog Remodel Group. Their customer service is outstanding, they are on time, on budget, and take extra time to explain all of the details before and while the project is underway. They completely remodeled our kitchen, removed walls, and added windows. We could not be happier with the results and the entire experience.”
Denise H. · Kitchen Remodel
4.8/5 Star Reviews

600+ reviews

View more

Spot our Bulldog Mobile around Cincinnati

Bulldog Remodel Group's red, black and white wrapped Tesla parked on a Cincinnati street
Side view of the Bulldog Remodel Group Tesla showing its kitchen, bathroom and windows services

Contact Us Today

Tell us about your project. We’ll take it from there.

Share a few details and a member of our team will reach out to get the ball rolling. There’s no obligation and no pressure to move forward.

(513) 657-3750

Call · Mon–Sun: 8am–8pm

Licensed #CBRC012649 · Lifetime warranty

By submitting, you agree we may contact you about your project. See our Privacy Policy.